Welding Time Calculation: Pass Sequence Planner

This planner lists the passes for a joint, root, hot pass, fill and cap, with the process and travel speed for each, and works out the arc time per joint, the cleaning time between passes, preparation time and the total time for a batch of joints at a realistic operator factor. It prints as a pass schedule.

  • Free, no sign-up
  • Runs in your browser
  • Built for Islamabad & Rawalpindi

This free calculator runs in your browser and needs JavaScript. If it does not load, call or WhatsApp us on +92 304 2435577 and we will do the calculation for you.

Welding time is usually underestimated because only the arc time is counted. Chipping slag, changing rods, moving, fitting up and checking take most of a welder’s day. The operator factor puts that back in.

What This Tool Does

It calculates arc minutes per pass from length and travel speed, cleaning per pass per metre, preparation per joint, total arc hours, and elapsed hours at the operator factor, with an optional labour cost.

Who It Is For

  • Estimators pricing welding labour.
  • Supervisors scheduling jobs.
  • Welders preparing a pass record.

How To Use It

  1. Add each pass type with the number of passes, travel speed and process.
  2. Enter the weld length per joint and the number of joints.
  3. Set cleaning, preparation and the operator factor.
  4. Click Plan passes and time.

How The Calculation Works

Arc minutes per pass = length (mm) ÷ travel speed (mm/min). Elapsed time = total arc time ÷ operator factor, and never less than arc + cleaning + preparation added together.

Worked Example

A 1 m butt joint: one E6010 root at 120 mm/min, two E7018 fill passes at 150 mm/min, one cap at 130 mm/min; four joints; 35% operator factor.

Input or result Value
Arc time per joint about 29.4 minutes
Arc time for 4 joints about 1.96 hours
Elapsed time at 35% about 5.6 hours

Almost three times the arc time, which is normal for manual welding.

Features And Benefits

  • Pass-by-pass schedule.
  • Operator factor for realistic hours.
  • Labour cost.

Assumptions And Accuracy Limits

  • Travel speeds are yours; the WPS sets parameters for code work.
  • It does not calculate the number of passes from groove area; use the joint preparation tool for volume.

Common Mistakes To Avoid

  • Counting only arc time. Arc time is usually a third or less of the welder’s day.
  • Forgetting cleaning. Slag removal between stick passes adds real minutes.
  • Using the fastest travel speed for every pass. Root passes are slower than fill passes.

Welding Labour In Islamabad And Rawalpindi

Welding labour in the twin cities is often priced per job or per day. Planning passes and time realistically helps when quoting fixed prices, and helps separate welding time from fitting, grinding and painting. Ramzan Steel Works quotes labour from planned hours.

Frequently Asked Questions

How do you calculate welding time?

Divide weld length by travel speed for each pass and add them up for arc time, then divide by the operator factor for elapsed time.

What is operator factor in welding?

The share of a welder’s working time with the arc on, typically 20–40% for manual welding.

How many passes does a weld need?

It depends on the joint volume and the bead size. Thicker plate and larger grooves need more fill passes.