This tool compares a welding machine, plus anything else on the same supply, against a generator’s continuous rating and shows how much of the generator the load would use. It flags phase and voltage mismatches, missing information, and the cases where the manufacturer’s own generator requirement should take over.

  • Free, no sign-up
  • Runs in your browser
  • Built for Islamabad & Rawalpindi

This free calculator runs in your browser and needs JavaScript. If it does not load, call or WhatsApp us on +92 304 2435577 and we will do the calculation for you.

It deliberately does not give a simple “safe” or “unsafe” answer. Arc starts pull short surges, inverter electronics are sensitive to voltage dips, and many machine manuals state a minimum generator size that is larger than the input kVA alone suggests. The tool puts the numbers side by side and tells you what is still unknown.

What This Tool Does

It works out the machine’s maximum input in kVA from the nameplate (volts and I1max, kVA, or kW and power factor), adds other loads, and divides by the generator’s continuous (prime) rating. It then checks the maker’s recommended generator size if you enter it, the generator’s peak rating, phase, voltage and whether the generator has voltage regulation.

Who It Is For

  • Welders working on sites without mains power, such as new plots and boundary walls.
  • Workshops buying or hiring a generator for load-shedding hours.
  • Contractors checking whether a hired generator will carry a machine and a grinder together.

How To Use It

  1. Read the welding machine’s input from the nameplate. For generator sizing use I1max, the current at maximum output.
  2. If the manual gives a recommended generator size, enter it. It is the most important figure on the page.
  3. Add other loads that will run at the same time, in kVA.
  4. Enter the generator’s continuous or prime rating. Do not use the larger “maximum” or standby figure here; there is a separate box for it.
  5. Set phase and voltage for both, tick whether the generator has AVR or is an inverter generator, and click Check generator.

Inputs And Units Explained

  • I1max — input current at maximum welding output. The generator has to supply this during the weld.
  • Maker's generator size — many inverter manuals state “use a generator of at least X kVA”. It overrides any calculation.
  • Continuous rating — what the generator can supply for hours. Peak or standby ratings are short-term.
  • AVR — automatic voltage regulation keeps the voltage steady when the arc strikes.

How The Calculation Works

Machine kVA = V × I1max ÷ 1000 for single-phase, or √3 × V × I1max ÷ 1000 for three-phase. If you enter kW, kVA = kW ÷ power factor.

Combined load = machine kVA + other loads. Load share = combined load ÷ generator continuous kVA × 100. Above 80% is flagged as tight, above 100% as over the rating. These are planning thresholds, not a standard.

Worked Example

A 230 V single-phase inverter with I1max 32 A, a 1.5 kVA grinder running alongside, and a 10 kVA single-phase generator with AVR. No maker’s figure entered.

Input or result Value
Machine maximum input 230 × 32 ÷ 1000 = 7.36 kVA
Combined load 7.36 + 1.5 = 8.86 kVA
Share of generator 8.86 ÷ 10 = 89%
Flags over 80% of the continuous rating; maker's requirement not entered

On paper it fits, with little margin. The next step is the machine manual: if it asks for 12 kVA, that settles it.

Features And Benefits

  • Puts the machine, other loads and generator on one page in the same units.
  • Names what is missing instead of hiding it inside an answer.
  • Checks phase and voltage, which are easy to overlook on hired equipment.
  • Summary you can send to a generator hire company.

Assumptions And Accuracy Limits

  • It cannot test voltage stability or waveform quality, which matter to inverter welders.
  • Motor loads such as compressors need several times their running kVA to start. Add that allowance yourself.
  • Generator ratings fall with heat and altitude. Summer site conditions in Pakistan reduce what a generator can deliver.
  • Earthing and protection on a generator supply must be set up by a qualified electrician.

Frequently Asked Questions

How much kVA generator is required for a welding machine?

At least the machine’s maximum input kVA plus other loads, with margin. Many makers recommend more, often 1.5 to 2 times the input kVA for inverters. Use the figure in your manual where there is one.

How do I choose a generator for a welding machine?

Find the machine’s I1max and voltage, convert to kVA, add other loads, and compare with the generator’s continuous rating. Check phase and voltage match and that the generator has voltage regulation.

Can I run an inverter welder on a small generator?

Only if the generator meets the maker’s requirement and holds its voltage steady. Undersized or unregulated generators can trip, or damage the welder’s electronics.

Can I weld using a generator?

Yes, it is common on sites without mains power. The generator must be large enough, regulated, and correctly earthed.

Should I use the continuous or the peak rating?

Continuous (prime). Peak or standby figures are for short periods and leave nothing for arc starts.

Related Free Tools

Get A Measured Quotation

For on-site welding where power is the problem, Ramzan Steel Works works on sites across Islamabad and Rawalpindi with its own equipment, and will tell you beforehand what supply the job needs.

Share this
0304-2435577WhatsApp Us